Commercial offices · for 4Space

Phased around what had to stay.

Commercial office flooring delivered across different floors of the same building, including one area where the existing desks had to remain in their established layout.

Commercial officelive constraints
Phasedfurniture moved in stages
Two floorsrecorded in project images
4Spacedelivery route
Bain – London
01

The challenge

On one floor the desks could not simply be cleared out. They had to remain in their established layout, creating an awkward working sequence around the furniture.

02

The delivery

The desks were moved in stages to one side, flooring installed to the released area, then the furniture was moved back into position so the next section could be completed.

03

The result

The flooring progressed without requiring the client’s established furniture layout to be dismantled — a practical response to a live-office constraint.